Sample daily log
Harbor Build — Pier 4 Renovation
- Address
- 1200 Embarcadero, San Francisco, CA
- Client
- North Pier Development
- Log date
- Saturday, July 18, 2026
Daily Summary
Crew completed deck formwork on the east bay and poured slab section B-3. Rebar inspection signed off at 10:15. Afternoon focus shifted to waterproofing prep along the seawall tie-in. Material delivery for tomorrow’s pour staged on the north laydown.
Workers on site: 12
Weather: 68°F, Partly cloudy, Wind 12 mph
Work Tags
Delays / Issues
Concrete pump delayed ~45 minutes due to Embarcadero traffic. Made up time by staging rebar and forms ahead of the pour.
Safety Notes
Hard-hat zone enforced at the seawall edge. One near-miss flagged: unsecured lumber near the east bay—corrected immediately. Toolbox talk covered fall protection on temporary decks.
Photos
East bay formwork ready for pour
Slab section B-3 after pour
Seawall waterproofing prep
North laydown — tomorrow’s materials