Sample daily log

Harbor Build — Pier 4 Renovation

Address
1200 Embarcadero, San Francisco, CA
Client
North Pier Development
Log date
Saturday, July 18, 2026

Daily Summary

Crew completed deck formwork on the east bay and poured slab section B-3. Rebar inspection signed off at 10:15. Afternoon focus shifted to waterproofing prep along the seawall tie-in. Material delivery for tomorrow’s pour staged on the north laydown.

Workers on site: 12

Weather: 68°F, Partly cloudy, Wind 12 mph

Work Tags

ConcreteFormworkWaterproofingInspectionMaterial staging

Delays / Issues

Concrete pump delayed ~45 minutes due to Embarcadero traffic. Made up time by staging rebar and forms ahead of the pour.

Safety Notes

Hard-hat zone enforced at the seawall edge. One near-miss flagged: unsecured lumber near the east bay—corrected immediately. Toolbox talk covered fall protection on temporary decks.

Photos

  • East bay formwork ready for pour

    East bay formwork ready for pour

  • Slab section B-3 after pour

    Slab section B-3 after pour

  • Seawall waterproofing prep

    Seawall waterproofing prep

  • North laydown — tomorrow’s materials

    North laydown — tomorrow’s materials